Phase No. I (0+82 - 10+00)

Walnut Street Paving Begins - June 22 Start Date

(June 22 - July 3) Subgrade, Earthwork, and Utilities

(July 6 - 31) Paving and Sidewalk

(Aug. 3 - 12) Final grading, Seeding, and Pavment Marking

Next
Next

Phase No. II (10+00 - 15+00)