Phase No. I (0+82 - 10+00)
Walnut Street Paving Begins - June 22 Start Date
(June 22 - July 3) Subgrade, Earthwork, and Utilities
(July 6 - 31) Paving and Sidewalk
(Aug. 3 - 12) Final grading, Seeding, and Pavment Marking